MoC finalises mines development schedules

24 Feb 2015

February 24: The Ministry of Coal (MoC) has finalised the timeline/schedule for the development of Schedule II and Schedule III coal mines/blocks with the approval of the competent authority, informed an official communique.

These timelines area corollary to the fact that according to provisions of the second coal Ordinance of 2014 and Coal Mines (Special Provisions) Rules, 2014, the performance bank guarantees of the successful bidder will have to be linked with the milestones for developing a coal mine till it reaches its peak rated capacity as specified in the approved mine plan.

Consequently, with regard to Schedule II mines, the time limit from the date of vesting/allotment order/zero date is one month for an application for transfer of statutory permission to the successful bidder while the approval of mine closure plan (if not approved earlier), will be six months and the EUP synchronisation, as per the approved mining plan.

Similarly, for Schedule III mines, completion of exploration and preparation of the geological report will have a deadline of 22 months for regionally explored blocks. The mining lease application will have a time limit of three months for “regionally explored” and “explored” blocks while the grant of mining lease will have a deadline of 24 months for both categories, amongst others.

Milestones for development of Schedule- II coal blocks/mines

   

Sl.
No.

Milestone

Time limit in months (from the date of vesting/allotment order/zero date)
[for schedule-11 blocks/mines]

1

Application for transfer of statutory permission to the successful bidder

1

2

Completion of transfer of statutory permissions obtained by prior allocatees

3

3

Reporting of deviations from approved mining plan (if any)

4

4

Ratification of deviations/approval of revised mining plan including mine closure plan (if necessary)

10

5

Approval of mine closure plan (if not approved earlier)

6 (in case of no deviation)

6

Opening of escrow account (if not opened earlier)

6 (in case of no deviation)

7

Schedule of production /reaching rated capacity.

As per approved Mining Plan

8

EUP synchronisation

As per approved Mining Plan

 

Milestones for development of Schedule-III coal blocks/mines

Sl.
No.

Milestone

Time limit in months (from the date of vesting / allotment
order/zero date)
[for schedule-ill blocks/mines]

Regionally
explored Blocks

Explored  blocks

1

Prospecting License

4

0

2

Completion of Exploration and preparation of
Geological Report (GR)

22

0

 

Events after preparation of GR

3

Mining lease application

3

3

4

Submission  of mining plan

6

6

5

Mining plan approval

11

11

6

Previous approval application

12

12

7

Previous approval

13

13

8

Forest clearance  application

11

11

9

Forest clearance

21

21

10

Environment clearance application

11

11

11

Environment clearance

21

21

12

Grant of mining lease

24

24

13

Land acquisition  (to reach rated capacity)

36/
42 (in case of Forest land)

36/
42 (in case of Forest land)

14

Opening of escrow a/c

37/
43 (in case of Forest land)

37/
43 (in case of Forest land)

15

Application for opening permission

37/
43 (in case of Forest land)

37/
43 (in case of Forest land)

16

Grant of opening permission

38/
44 (in case of Forest land)

38/
44 (in case of Forest land)

17

Schedule of production /
reaching rated capacity.

As per approved
Mining Plan

As per approved
Mining Plan

18

EUP synchronisation

As per approved
Mining Plan

As per approved
Mining Plan